Details: the work of and commissioning of main rail table of wagon tippler no. 3 including dismantling and removal of old one and transportation, shifting, installation and commissioning of new one of chp, btps, obra. scope of work:1. making scaffolding for dismantling of existing main rail beam.2. arrangement of all t&p, hydraulic jacks, special tools & tackles, fasteners & consumables required in this work.3. wagon tippler to be lock on ground position by providing temporary support.4. dismantling of existing rail beam.5. suitable crane, hydra & trailer made available for transportation of new rail table to wagon tippler no. 3 by own means and cost.6. removal of dismantled rail beam, platform etc. to scrapyard or at the place told by site in charge of the chd-ii, btps obra.7. required high skilled, semi-skilled and unskilled manpower.8. clean up at site all debris and temporary structures on daily basis and final clean up
Sector: Generation