Details: construction of embankment with approved material obtained from borrow pits with a lift up to 1.5 meter transporting to sites spreading grading to require and compaction to meet requirement of table 300.1 & 300.2 with a lead up to 1000 meter as per mord technical specification clause 301.5 mord sepecification 301.5(i) s.no. 3.4(ordinary soil) construction of subgrade and earthen shoulder with approved matarial obtained from borrow pit with all lift and lead, transporting site ,spreading,grading to required and compacted to meet requirement of table 300.2 with lead upto 1000 m as per technical specification clause 300.1 including stablization with 2% slaked lime including its mixing with rotavetor complete cement treated subbaseproviding, laying, spreading material on prepared sub grade adding cement @ 2% by weight to the spread material manually mixing in place with rotavator and compacting with the road roller at omc to achieve the desired unconfined compressive strength to form
Sector: PWD