Details: item description/ heading total wt. of ms materials for the work of dismantling total wt. of ms materials for the work of fabrication & (loss of ms materials to be compensated from serviceable materials of scrap yard and dead unit) removing of scrap material from site & transportation from site to scrap yard and serviceble material from different plant site to work site. cost of site preparation:- a) supervisor 06 nos. @ rs.734.00 = rs.4404.00, b) usw 36 nos. @ rs. 522.00 = rs.18792.00 total rs. 23196.00 cost of : dismantling of conveyor belt , drive unit, gear box, motor base, refitting/ commissioning/ testing and make ready for operation. cost of transportation of drums, coupling, gear box to the work shop, repairing/machineing of damaged portions and shifting back to the site. total impact of gst for the purpose of ctc
Sector: Mining