Details: providing and laying tack coat over existing bt surface using 2 kgs of bitumen emulsion (rs1) per 10 m² for preparatory to another bituminous construction over it including cost of material, labour charges, rentals for machinery, fuel and all other incidental charges etc., complete as per clause 503 of morth rev-5. providing and laying 50 mm consolidated thick dense bituminous macadam using 0.24 m³ of 26.50-13.20 mm, 0..25 m³ of 13.20-2.36 mm and 0.23 m³ of 2.36 mm & below and with 53.20 kgs of vg30 / vg40 bitumen for premixing per 10 m² including cost and conveyance of all materials to cmp site, heating the bitumen and aggregate to required temperature and mixing them in required temperature in central hot mix plant 20-30 ton capacity, conveying the mix by tipper trucks to work site, spreading the mix to uniform thickness of 50mm with paver to the specified grades and cross sections and compacted by vibratory / pneumatic roller to the required density etc, including labour for attendi
Sector: RDPR