Details: earth work excavation and depositing on bank with initial lead and lift in hard gravelly soil, hard stiff clay, black cotton soil, hard red earth,shales, murram, and earth muds with 50% fair sized boulders as per ss 20b for narrow foundation. filling with river sand including cost and coveyance of all materials to work site and all labour charges etc. cement concrete 1:4:8 mix using 40mm metal including cost and conveyanceof all materials to work site and all labour charges etc. brick work in cement mortar 1:5 mix using country bricks including cost and conveyance of all materials to site and all labour charges etc complete brick work in c.m 1:5 mix using country bricks incuding cost and conveyance and all labour charges etc. rcc 1:1.5:3 mix using 20mm metal including cost and conveyance and all labour charges etc.up to basement rcc 1:1.5:3 mix using 20mm metal including cost and conveyance and all labour charges etc.for super structure supplying and errecting for sides & soffits in
Sector: RDPR