Details: civil portion of work:-earth work in excavation of foundation trenches in hard soil including dressing of sides and levelling the bed up to the required depth and depositing the excavated materials away from the work site within 50m initial lead & 1.5m initial lifts with sundries & t&p required for the work complete including cost of all labour,labour cess, t&p, sundries etc. as directed by the engineer in charge.(i) farmer rest shed (ii) cover pindi (iii) internal road filling in foundation trenches and plinth, with excavated earth including laying the earth in layers not exceeding 23.5 cm thick ramming & watering with all leads & lifts including cost of all labour,t&p completed as directed by the engineer-in-charge.(i) farmer rest shed (ii) cover pindi (iii) internal road supplying and filling in foundation and plinth with good quality river sand including watering, ramming with cost, conveyances, royalties of all materials and cost of all labour with t&p required for the work etc. c
Sector: PWD