Details: safe loading carriage including unloading and proper stacking of following materials from central store barabanki / je store to site of work a) stp pole a) acsr weasal conductor. b) transformer 25 kva /10 kva/16kva/63kva/100kva d) pcc pole 8.5 mtr long e) stay set complete f)11 kv xlpe cable 3x120 mm /3x 70mm/ 3x 185 mm e) 11kv pin/insulator and disc/fitting etc. f) 11kv metering cubical unit g) 11 kv double pole ct/pt unit f) other line material like steel section, gi wire etc g) cable jointing kit 3x70 mm/3x120 mm/3x185mm h) single phase abc/ 3x 50 abc mm i) db box dragging of stp/pcc pole of single pcc pole 8.5 mtr long with accessory as per norms. fabrication, of double pole for cable exposure with st pole 8.5 m long including of one nos. top channel of size 100x50 mm -2.25 m, two nos. dropper angle with clamps and nut bolts, grouting of each pole below ground 0.268 cu.m in ratio 1:4:8 cement, coarse sand & brick ballast, plinthing around the pole 300 mm above ground level. t
Sector: Distribution