Details: earthwork in excavation in foundation in ordinary soil including lift up to 1.50 m. and lead up to 30.00m. including all complete as per s.i.no. 251 concrete with 40 mm gauge b/ballast,fine sand of 1.25 fm.and cement in proportion of 12:6:1 in foundation and under floor i/c supply of all material labour and t&p etc.all complete as per s.i.no.273. class m150 rick work in cement & fine sand morter in 1:4 in foundation including supply of all labour material etc. up to proper completion of works. asper si no. 305 12mm thick plastering in 1:4 cement and fine sand mortar on rough surface i/c all complete as per si no. 584 providing and laying of red colour interlocking concreat block pavements having thickness 80mm including leveling and dressing of surface to required level and ,spreading and moisting 30 mm thick locak sand on bed , filling joints with local sand etc for proper completion of the work as per drawing and technical specification clause 1504 as per mord specification no 1