Details: item short description yokogawa dcs av & ms patch update system item text scope of work for installation and commissioning: 4.5.,,installation, commissioning & deployment 4.5.1.,,vendor to develop and share project implementation methodologyto ensure completion of project at stipulated time 4.5.2.,,the detail design and architecture shall be implemented on dueapproval of bpcl with necessary requirements and any if amendments as ifrequired 4.5.3.,,vendor shall devise functional design specification and detailedspecifications complying with latest isa/iec 62443 series of iacsstandards 4.5.4.,,the proposed solution has to be tested in bpcl environmentwithout disturbing the process control network 4.5.5.,,the equipment must be delivered at the respective locations.costs for obtaining necessary road permits, insurance, storagefacilities and other related permits will be the responsibility of thebidder. vendor representative should be available at the site forunloading and safe storage