Description: REPLACEMENT OF VCB UNDER EDC ETAWAH BUSINESS PLAN 2024 25 ON SEMI TURNKEY BASIS Name of Work Replacement Of Different Make 11 Kv VCB Under Business Plan 2024 25 in the area of EDC Etawah on Semi Turnkey basis
Details: Carriage & Erection of Different Make 11 Kv VCB with Incomming/Outgoing Pannel from Store Center, Etawah to site of work Under Business Plan 2024-25 through the Kacha and Pakka road including the work of its loading and unloading at the respective ends including the cost of arrangement of labour, T&P, carrier etc. required for proper completion of work. Removal of old Incoming and outgoing VCB connections and dismantling from substation Safely & Carefully Installation of New 11 Kv Incoming (CTR 600/300/5A)/Outgoing VCB (CTR 200/100/5A) and making all connection Properly with proper commissining of VCB. Back Carriage of Scrap/old/damaged used VCB from Pit Site to JStore Center Kunera Etawah.
Sector: Distribution